How SGH Kept Holland Court Running During Urgent Switchboard Maintenance
Quick Summary
SGH supplied temporary power at the Holland Court residential development in Flemington, Melbourne, after urgent maintenance on the main distribution board was confirmed late in the day. Our team mobilised three 500 kVA generators and had temporary power in place by the following morning. The maintenance finished ahead of schedule and within the approved budget, with no reported disruption to site activities or nearby residents.
About the Holland Court Development
Holland Court is a completed residential redevelopment in Flemington. Building Communities, a not-for-profit consortium appointed by Homes Victoria, delivered 286 homes, including social housing, affordable rental homes and Specialist Disability Accommodation. Homes Victoria project overview Homes Victoria.
|
Project |
Holland Court residential development |
|
Location |
Flemington, Melbourne, VIC |
|
Power requirement |
Temporary power for the shared substation serving both the construction site and the residential development during main distribution board maintenance and a partial upgrade |
|
Response |
Late-day call-out, with temporary power in place by the following morning |
|
Equipment supplied |
Three 500 kVA generators, two 3,000-litre fuel cubes, temporary cabling and acoustic barriers |
|
SGH scope |
Site inspection, recommendations, setup, commissioning and dismantling |
The Challenge: Critical Maintenance at Short Notice
Late in the day, the site team confirmed that the main distribution board needed urgent maintenance. The work could interrupt power, so the site needed a temporary supply ready for the following morning.
Construction workers and machinery were still operating on site. Around the development, residents were going about their day, with school drop-offs and local traffic adding to the activity. With homes, schools, support centres and a supermarket nearby, equipment placement and generator noise had to be considered from the outset.
The SGH Solution: Temporary Power by the Following Morning

Our team began coordinating the response as soon as the call came in. We inspected the site, recommended a setup and managed the job through to dismantling once the maintenance was complete.
We supplied and commissioned:
- Three 500 kVA generators to supply the shared substation that served both the construction site and the residential development.
- Two 3,000-litre fuel cubes to support the generators.
- Temporary power cabling to connect the generators to the site.
- Acoustic barriers to limit generator noise near homes and businesses.
Our team stayed in close contact with the site’s decision-makers to coordinate the setup and changeover around the maintenance work. The changeover was completed with no reported impact on site instrumentation or residents’ household devices. SGH temporary power generator hire.
The Outcome: Maintenance Completed Ahead of Schedule
SGH had temporary power in place by the following morning. The changeover and partial upgrade took approximately four days, with the work finishing roughly three days ahead of schedule and within the approved budget. Site activities continued, and the project team reported no disruption to residents.
Having one team manage the temporary power setup, from inspection through to dismantling, gave the site a single point of coordination while it focused on completing the maintenance.
Frequently Asked Questions
Can temporary generators keep a site running during switchboard maintenance?
Yes. A temporary generator system can supply the site loads that need to stay operational while switchboard maintenance is carried out. The setup depends on which equipment needs power, how the site is wired and how much access is available for generators and cabling.
How can generator noise be managed near homes?
Generator placement and acoustic barriers can help limit noise at nearby homes and businesses. At Holland Court, SGH supplied acoustic barriers as part of the temporary power setup.
Can SGH provide temporary power at short notice in Melbourne?
SGH provides emergency generator hire and temporary power support in Melbourne. At Holland Court, our team responded to a late-day call and had temporary power in place by the following morning.
Need Temporary Power for Electrical Maintenance?
Whether you have a scheduled switchboard shutdown or urgent work that needs to start tomorrow, talk to SGH about your site, the equipment that needs to stay powered and the time available for setup. Request a Temporary Power Quote